486 WorkRate |
Name : _________________ |
||
If Ann does a job in 5 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 6 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
+( ) |
|
( )+ |
++[[ ]]++ |
||