410  WorkRate
Together, how long? 1

Name : _________________

 

refresh

If Ann does a job in 4 days, and Bob does it in 2 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 10 days, and Bob does it in 3 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 9 days, and Bob does it in 2 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 8 days, and Bob does it in 5 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 10 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 8 days, and Bob does it in 3 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 9 days, and Bob does it in 2 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 5 days, and Bob does it in 3 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 3 days, and Bob does it in 9 days, how long do they take together? (Nearest to the 10th...)



If Ann does a job in 10 days, and Bob does it in 3 days, how long do they take together? (Nearest to the 10th...)



+(         )

 

(         )+

++[[          ]]++

410    1.3 2.3 1.6 3.1 3.8 ( 12.1 )   2.2 1.6 1.9 2.2 2.3 ( 10.2 )   [[ 22.3 ]]